華星東方承建的河北省衡水市安平縣生活垃圾焚燒發(fā)電項(xiàng)目煙氣凈化工程通過72+24小時(shí)試運(yùn)行

中國電力網(wǎng)發(fā)布時(shí)間:2023-01-31 14:02:24

華星東方承建的河北省衡水市安平縣生活垃圾焚燒發(fā)電項(xiàng)目煙氣凈化工程于2021年08月01日通過72+24小時(shí)試運(yùn)行。

The FGC project constructed by Huaxing for Anping waste incineration power plant in Hengshui, Hebei passed 72+24 hours trial operation onAugust01, 2021.

該項(xiàng)目建設(shè)總處理規(guī)模為800 t/d,建設(shè)2x400t/d的機(jī)械爐排垃圾焚燒生產(chǎn)線,配置1x18MW汽輪發(fā)電機(jī)組。煙氣處理采用“爐內(nèi)SNCR+半干法(旋轉(zhuǎn)噴霧)+氫氧化鈉溶液噴射系統(tǒng)+干法(干粉噴射)+活性炭吸附+袋式除塵+濕法(預(yù)留)+SCR(預(yù)留)+飛灰輸送、存儲(chǔ)及穩(wěn)定化工藝”的煙氣凈化工藝,為我司EPC工程。

The plant has an average waste treatment capacity of 800 t/d, construction of 2x400t/d mechanical grate waste incineration production line, equipped with 1x18 MWsteam turbine generator. The FGC process applied "in-furnace SNCR + semi-dry rotary spray + Sodium hydroxide solution injection system + dry method with dry powder injection + activated carbon adsorption + bag filter + wet reserved + SCR reserved + fly ash conveying, storage and stabilization process". It is an EPC project of Huaxing.

華星東方在河北省的業(yè)績涵蓋包括:保定一期、二期、衡水、安平、定州、滄州一期、石家莊、行唐、曹妃甸、圍場、順平、唐山一期、二期、張家口北、固安、三河、香河、灤州、沙河、石家莊夏能炘等多個(gè)項(xiàng)目。

The achievements of Huaxing East in Hebei Province include Baoding phase I & II, Hengshui, Anping, Dingzhou, Cangzhou phase I, Shijiazhuang, Xingtang,Caofeidian, Weichang, Shunping, Tangshan phase I & II, North Zhangjiakou, Gu'an, Sanhe, Xianghe, Luanzhou, Shahe, Xia Nenxin of Shijiazhuang, etc.